How do I change the timeline in MS Project?

Set Chronological Date Ranges

  1. On the Quick Launch, click Projects.
  2. Click anywhere on the timeline to open the Timeline tab, then in the Show/Hide group, click Set Date Range.
  3. In the Set timeline dates box, select Set custom dates, enter the desired start and end dates, and click OK.

How to change time in weeks in MS Project?

In Project, the default unit for task duration is days, but you can change it to minutes, hours, weeks, or months:

  1. Choose File > Options.
  2. In the Project Options dialog box, select Schedule.
  3. Under Scheduling options for this project, select a duration unit from the Duration is entered in list.

How to delete data from MS Project timeline?

Choose Format…Bar Styles from the Bar Styles group. In the Bar Styles dialog box, select the row from which you want to remove the date. Select the Text tab in Bar Styles and remove the date field from the right.

How do I change the date range of a Gantt chart?

Click any date above the task bars in your Gantt chart. One click selects all the data, you right click on it and choose Format Axis from the context menu. Under Axis Options, change Minimum to Fixed and enter the number you wrote down in the previous step.

How to create working days on Saturday and Sunday in MS Project?

Allow weekend work for a task

  1. Step 1: Create an additional schedule. Create a new calendar that allows working on Saturdays and Sundays. …
  2. Step 2: Maintain working times in the new calendar. Select work weeks, then double-click the first entry: …
  3. Step 3: Associate your task with the new calendar. …
  4. 3 comments.

How to create a timetable in MS Project?

This can be achieved by going to the Tools > Options menu item and selecting the “View” tab in the Options dialog box that appears. Open the “Date format” drop-down menu and select the appropriate format, which also includes hours and minutes. This now allows the hour and minute to be specified for each timestamp field in MS Project.

How to hide current dateline in MS Project?

Right-click in the Gantt Chart, choose Gridlines. Select the current date line and set the line style to the first choice (none).

How to remove green line in MS Project?

In a Gantt Chart view, go to the Format tab, Gridlines, and select the gridlines. Select the Current Date row and first change the Type to the blank option.

How do I add data to a Gantt chart?

To change the date format in the Gantt bars, click Layout on the Format menu, and then click the date format you want in the Date Format box. Click on the other bars to add project information to them, making sure you’re pointing to the bars and not the space around them.

How do I change the date format in a chart?

View or change data on a category axis

  1. In the chart, right-click the category axis, and then click Format Axis.
  2. In the Format Axis area, select the Axis Options tab.
  3. Expand Axis Options, then under Axis Type ensure Date Axis is selected.
  4. Under Units, next to Base, select either Days, Months, or Years. Notes: